Figure 8-5 Removing the cabinet sliding base fasteners
Step 2 Remove the sliding base fasteners for other cabinets inside the pre-fab. module in
the same way.
----End
8.3 Removing Sliding Door Fasteners
Prerequisites
The pre-fab. modules have been installed.
Preparations
Tool: adjustable wrench
Materials: none
Documents: none
Skill requirement: common technician
Context
The three hot aisle sealing doors and the door between the entrance hall and the
equipment compartment in a pre-fab. module are all glass sliding doors. Fasteners
are installed on the glass sliding doors to prevent the doors from being damaged
during transportation.
After pre-fab. modules are installed and secured, the fasteners need to be
removed so that the sliding doors can work properly.
Issue 07 (2022-12-15)
Copyright © Huawei Digital Power Technologies Co., Ltd.
8 Removing Transport Protection Materials
72