Procedure
Step 1 Cut open the protective cover using a utility knife and remove the protective cover.
----End

5.1.3 Hoisting Pre-fab. Modules

Prerequisites
To facilitate subsequent installation, ensure that pre-fab. modules are level after
hoisting.
Context
The crane and steel ropes must meet the pre-fab. module hoisting requirements.
Table 5-1 Parameters for hoisting pre-fab. modules
Weight
Net weight: <
14,000 kg
Hoisting Precautions
Stage
Before hoisting
Issue 07 (2022-12-15)
NO TE
When removing the protective cover, take protective measures for working at heights.
NO TICE
Select an appropriate crane based on standards of the crane company, and
ask a professional to assess the crane onsite.
The hoisting ropes are available.
The positions of pre-fab. module corner fittings are correctly marked.
The doors of pre-fab. modules to be hoisted are closed.
The weather is good without wind when pre-fab. modules need to be hoisted
outdoors.
Steel Rope
Length
> 12.5 m
Precautions
Ensure that the crane and steel ropes provide the required
bearing capacity.
Ensure that the steel ropes are securely connected.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Steel Rope
Dimensions (H x W x D)
Quantity
4 PCS
2896 mm x 2438 mm x 12192
mm
5 Installing Pre-fab. Modules
41

Advertisement

Table of Contents
loading

Table of Contents