Location inspection
No.
1
The main circuit breaker of external switchboard has parameters according to specification [Ir=
280A; Ii=1600A]
2
Write down the parameters in the comment section & take a picture of the breaker and its settings
3
Is the base area dry?
4
Check if the foundation has the recommended dimensions and shape in the operating manual and
take a picture with the straight edge. (See image below)
5
Is the position of the power supply cable suitable to the dimension of the charger cable glands?
Figure 3-1
Installation and Commissioning Checklist for SICHARGE UC
Product Information, 03/2023, A5E52548271-AA
Checklist item
Base area of charging station
Area for the cable routing
Area for cable inlet
Reinforced concrete
Example for footprint and foundation
SICHARGE UC Charger
3.1 Pre-Installation
P
F
N/A