Transbox Assy Function Validation Procedure

1.) Turn on the system. Refer to
check AP950 Assy function. The system must show correct operation as described on sequence.
2)Check the peripheral operation. Refer to
peripheral operation. All peripheral must work correctly as described Section 4-5.
4-9-14

Fuse set Function Validation Procedure

1.) Turn on the system. Refer to
check Transbox Assy function. The system must show correct operation as described on sequence.
2.) Check the peripheral operation. Refer to
the peripheral operation. All peripheral must work correctly as described Section 4-5.
4-9-15

ARP Assy Function Validation Procedure

1.) ARP Assy function can be validated by the result of 'Peripheral Test'. Once ARP Assy is replaced,
do peripheral test in order to confirm the successful installation. Refer to the
Checks" on page
4-9-16
ASIG ASSY Function Validation Procedure
1.) Turn on the system. R
2.) Check the basic function of system's different modes. Refer to
on page 4-8
5
3-5-1 "Power On/Boot Up" on page 3-11
3-5-1 "Power On/Boot Up" on page 3-11
4-26.
and Refer to
10-5-2-1 "System Checks" on page
Section 4-9 - Board Function Checks
Section 4-5 "Peripheral Checks" on page 4-26
Section 4-5 "Peripheral Checks" on page 4-26
4-3-4 "System B/M-Mode Checks"
10-8.
LOGIQ™ P5 S
M
EVICE
ANUAL
for power up sequence to
to confirm the
for power up sequence to
to confirm
Section 4-5 "Peripheral