Figure 8-1 Active power control
Reactive Power Control
Large-scale PV plants are required to adjust the voltage at the grid-tied point. Power grid
scheduling personnel enable the PV plant to absorb or add the reactive power at the grid-tied
point, that is, to enable the reactive power compensation, based on the real-time reactive
power transmission status in the power grid.
Because of permission restriction, log in as Special User. Choose Settings > Reactive power
control to access the target page.