8.3.4 Power Factor Fix Control

If the PV plant is required to generate a constant power factor at the grid-tied point and the
inverter is required to adjust the real-time reactive power based on the preset power factor, set
Reactive power control mode to Power factor fix control.
Figure 8-12 Power factor fix control
Issue 04 (2018-04-10)
If the inverter needs to run with specified maximum power in certain periods of a day, add setting
records based on site requirements.
The range specified for Reactive Power is relevant with the grid code and the model.
When multiple time points are set, the inverter will run with the maximum power specified for the
time point that is earlier than and the closest to the system current time point. For example, if you
add 00:00:00 and 12:00:00 on the WebUI and the system current time point is 14:30:00, the inverter
will run with the maximum power specified for 12:00:00.