Figure 8-7 Synchronizing the clock source
1.
2.
3.
Set Active power control mode to Remote output control.
Figure 8-8 Remote Output Control
Issue 04 (2018-04-10)
Clock source: Set NTP.
Server: Set the server IP address or domain name.
NTP synchronization test: Check the time synchronization status.
Control area: Set the area where the remote output control function is used. To enable the function
in some areas, the license needs to be imported and enabled.
Output control duration: Set the time required for the inverter to change its output power from 0%
to 100% or from 100% to 0%.
PV plant ID: Set the ID assigned by the power company to the SmartLogger.
Remote output control server: Set the server IP address or domain name.
If the connection between the SmartLogger and the server is abnormal, obtain the output control file
in .data format from the website of the power company and import the file.
After the SmartLogger connects to the server, you can export the relevant file.