Time parameters

Siemens Building Technologies
HVAC Products

4.2 Program sequence

The sequence diagrams show the program sequence in detail (refer to «Sequence
diagrams»).

4.2.1 Parameters

The most important time parameters for the program sequence are the following (for
values, refer to the list of parameters):
Prepurge time
Preignition time / circulation time heavy oil
Safety time 1 (TSA1)
Safety time 2 (TSA2)
Interval 1
Interval 2
Postpurge time 1 (t8-1) with FGR damper shut (this part of the postpurge time is
always executed)
Postpurge time 3 (t8-3) with FGR damper open (this part of the postpurge time will be
interrupted when there is demand for heat)
Postpurging in the lockout phase (if G = ON before lockout occurred)
All the times mentioned above - with the exception of «Postpurging in the lockout
phase» - depend on the type of fuel, which means that different times can be set for oil
and gas.
The prepurge time and the safety times are safety-related. This means that, using the
AZL51..., the heating engineer can only readjust them in the «safe» direction (against
internal maximum or minimum values).
In other words, «ts» times can only be shortened and «tv» times can only be extended.
Basic Documentation LMV51...
4 Burner control
41/278
CC1P7550en
01.10.2003