Figure 4-62 IVS Rear panel
Step 3 Connect one end of the power cable to the input power port on the power module
and the other end to the PDU2000 in the cabinet.
----End

4.4 Verifying the Installation

Cabinet Installation Check
Table 4-8 Cabinet installation check items
No.
1
2
3
4
5
6
7
8
Issue 01 (2020-11-30)
NO TE
After connecting the power cable, turn on the power switch on the panel to start the
device.
Check That
The cabinet position is consistent with the
equipment room layout diagram.
All bolts are tightened, especially the bolts used
for electric connection. Flat washers and spring
washers are installed properly.
The cabinet is clean and free of dust and other
materials.
The cabinet is clean and complies with dustproof
requirements.
The paint on the cabinet exterior is intact.
Promptly repaint the cabinet exterior if necessary
to prevent corrosion.
The cabinet door and lock work properly.
All labels are correct, clear, and complete.
The cabinet has no waste tape, cable ties, paper,
or packing materials around it.
Copyright © Huawei Technologies Co., Ltd.
4 Installation Guide
Check Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed