5.2.1 Powering on Devices

Prerequisites
Procedure
Step 1 Switch on the smart cooling product circuit breaker in the upstream PDB.
The electric heating belt of the crankcase starts working. Before starting the
compressor, ensure that the electric heating belt of the crankcase has been
preheated for more than 12 hours. Otherwise, maintenance is not performed.
Step 2 Commission the system after the electric heating belt of the crankcase has been
preheated for 12 hours.
----End

5.2.2 Performing Initial Configuration

Prerequisites
One end of the straight-through cable has been connected to the communications
port on the NetCol8000-A0131, and the other end has been connected to the
COM port on the ECC800-Pro.
Procedure
Step 1 Add the NetCol8000-A0131.
1.
2.
Issue 01 (2020-11-30)
Check that the humidifier water inlet pipe and drainpipe are correctly
connected, that the thermal insulation foam is intact, and that refrigerant has
been charged.
Check that the smart cooling product circuit breaker in the upstream PDB is
OFF.
Check that the power cable is correctly connected and that the input voltage
meets requirements.
Check that the smart cooling product control unit and the ECC800-Pro are
correctly connected.
NO TICE
Log in to the ECC800 WebUI as an administrator.
Add the NetCol8000-A0131.
Table 5-1 Adding a smart cooling product
Path
Parameter
Choose
Device
System
Attribute
Copyright © Huawei Technologies Co., Ltd.
5 Power-On Commissioning
Setting
Select Air Conditioner from the drop-
down list box.
112