Huawei FusionModule 1000B Maintenance Manual page 188

Air-cooled it solution
Table of Contents

Advertisement

FusionModule1000B Air-Cooled IT Solution
Maintenance Guide
Figure 6-98 Installing the battery protective panel
Step 7 Check whether the new VESDA batteries are working properly.
----End
Follow-up Procedure
Dispose of the removed VESDA power box batteries that are confirmed faulty.
Issue 02 (2017-01-10)
Turn on the standby power switch. If the power fault indicator is off, the batteries are working properly.