Step 6 Reconnect the cables and the power plug of the VCN500.
Step 7 Check whether the new VCN500 is working properly.
----End
Follow-up Procedure
Dispose of the removed VCN500 that is confirmed faulty.

6.3.10 Replacing a LAN Switch

Prerequisites
Impact on the System
The monitoring system or devices in the area where the LAN switch is to be replaced may be
shut down.
Preparations
Tools: Phillips screwdriver, ESD gloves, marker
Materials: spare LAN switch
Documents required: documents delivered with the LAN switch
Issue 02 (2017-01-10)
Figure 6-30 Installing a VCN500
If the VCN500 power indicator is steady green, the VCN500 is working properly.
If the network port ACT indicator blinks green, data transmission is normal.
If the hard disk active indicator blinks green, the hard disk reads data properly.
A LAN switch needs to be replaced.
A spare LAN switch of the same model is available and functional.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
111

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusionmodule 1000

Table of Contents