3. CC-Link COMMUNICATION FUNCTIONS
(4) How to wire the CC-Link terminal block (TE5)
(a) Strip the sheath of the cable and separate the internal wires and braided shield.
(b) Strip the sheaths of the braided shield and internal wires and twist the cores.
(c) Match and twist the wires and braided shield of the cable connected to the preceding axis or PLC
and the corresponding wires and braided shield of the cable connected to the subsequent axis.
(d) For the last axis, work the termination resistor supplied to the CC-Link master unit as shown
below.
(10mm (0.394in.))
(e) Insert the core of the cable into the opening and tighten it with a flat-blade screwdriver so that it
will not come off. (Tightening torque: 0.5 to 0.6N m) When inserting the wire into the opening,
make sure that the terminal screw is fully loose.
To the preceding station
Braided shield
3-core twisted pair cable
Termination register
(10mm (0.394in.))
Cut
Cut
CC-Link terminal block
Opening
Wire
To the next
station
or PLC
POINT
Do not solder the cores as it may cause a contact fault.
Approx. 10mm (0.394in.)
Remove sheath
Remove sheath
Loosen Tighten
Flat blade screwdriver
Tip thickness 0.4 to 0.6mm (0.016 to 0.024in.)
Full wide 2.5 to 3.5mm (0.098 to 0.138in.)
3 - 4
Fold lead wire