Commissioning
3.4 Configuring the drive unit using the STARTER commissioning tool
3.4.6

Loading the project to the drive unit

Introduction
To load the project to the drive unit, proceed as follows:
Steps
1. Click Connect to target system. An ONLINE connection is established and an
2. You changed the data OFFLINE and now have to load it to the target system. Carry out
94
ONLINE/OFFLINE comparison takes place. If any discrepancies are identified, they are
displayed (see screenshot below).
Figure 3-18
ONLINE/OFFLINE comparison (example)
the following:
– <-- Download in the "ONLINE/OFFLINE comparison" dialog box
– When the system asks "Are you sure?", click Yes. The system now starts loading the
data.
– When the system informs you that the data was successfully loaded to the target
system, click OK.
– Click OK for "Load from RAM to ROM".
Commissioning Manual, (IH2), V2.6, 10/2008 Edition, 6SL3097-2AA00-0BP3