FusionModule2000 Smart Modular Data Center
Installation Guide
Figure 10-3 Installing sealing plates away from the aisle
(1) Column
----End

10.3 Installing Skylights

10.3.1 Installing Control, Flat, and Rotating Skylights

Context
Install skylights one by one from one end of the smart module based on the site engineering
layout diagram.
The recommended skylight layout is as follows:
Preparations
Tool: Phillips screwdriver, adjustable wrench
Issue 02 (2018-03-31)
Install control skylights at the outermost positions at both ends of the aisle.
Deploy rotating skylights and flat skylights alternately.
Preferentially deploy rotating skylights beside control skylights.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Installing the Aisle Containment
97