Materials: skylight connective plate, skylight plate, cable separation plate
Document: skylight installation position diagram, onsite engineering layout diagram
Procedure
Step 1 (Optional) Install cable separation plates on control skylights.
Cable separation plates need to be installed only for control skylights.
1.
2.
Step 2 Keep the skylight connective plates flush with the end plane of the cabinet top sealing plate in
the aisle containment. Secure the two skylight connective plates to the appropriate mounting
holes by partially tightening four M8x20 screws, as shown by (1) in
Issue 02 (2018-03-31)
Interconnect cable separation plates, as shown by (1) and (2) in
Figure 10-4 Installing cable separation plates
Use four M5x10 tapping screws to secure the cable separation plates to the control
skylight plate, as shown by (3) in
In the single-row aisle scenario, keep one skylight connective plate flush with the end plane of the
cabinet top sealing plate and one skylight connective plate flush with the sealing plate.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Installing the Aisle Containment
Figure
10-4.
Figure
10-4.
Figure
10-5.
98

Advertisement

Table of Contents
loading

Table of Contents