Verify that the rubber strips are closely attached to the glass doors.
The rubber strip baffle plate outside the glass doors should face the aisle containment, and
the top of the rubber strip should be flush with the glass doors, as shown by (1) in
10-34.
The rubber strip attaching surfaces at the inner side of the glass doors should be parallel,
and the top of the rubber strip should be flush with the glass doors, as shown by (2) in
Figure
The rubber strip baffle plates under the glass doors should be installed outside the aisle
containment, and the rubber strip length at the bottom should be the same as the width of
the glass doors, as shown by (3) in
2.
3.
4.
5.
6.
Issue 02 (2018-03-31)
10-34.
Figure 10-34 Install glass door rubber strips
Snap the guide rail into the upper frame mounting kit. Secure the guide rail to the door
frame using five M6x16 screw assemblies, as shown by (1) in
Push the glass doors into the guide rail, and pull the glass doors outwards to allow the
door handles to pass through the posts, as shown by (2) and (3) in
Push the stop blocks into the guide rail with the screw holes facing outwards, as shown
by (4) in
Figure
10-35.
Tighten the two M6 screws at both ends of the guide rail, as shown by (5) in
10-35.
Push the stop blocks outwards to the screws at the ends of the guide rail, and use a
flat-head screwdriver to secure the stop blocks with two M6 screws, as shown by (6) and
(7) in
Figure
10-35.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Installing the Aisle Containment
Figure
10-34.
Figure
Figure
10-35.
Figure
10-35.
Figure
125

Advertisement

Table of Contents
loading

Table of Contents