Figure 15-9 Installing a LAN switch
Step 3 Connect the LAN switch power cable to the rPDU.
----End
Follow-up Procedure
If a 24-port LAN switch is configured, two power modules need to be installed for the LAN
switch onsite. Insert the power modules into the power slots of the 24-port LAN switch, and
tighten the captive screws on the power module panel.
Figure 15-10 Installing the power modules for a 24-port LAN switch

15.1.4 Installing an ECC800

Preparations
Tool: Phillips screwdriver
Materials: ECC800, SIM card, 2.4G antenna, 3G antenna
Document: installation position diagram for monitoring devices in the network cabinet
Issue 02 (2018-03-31)
The positions of power cable ports vary depending on the LAN switch models. Connect the power cable
based on the actual power port of the LAN switch.