FusionModule2000 Smart Modular Data Center
Installation Guide
Figure 10-7 Installing a skylight connective plate
(1) Column
(3) Sealing plate near an aisle
Step 2 Extend the two telescopic edges to an appropriate length and secure each using one M6 bolt.
Figure 10-8 Adjusting the length of a telescopic edge
Step 3 Secure the telescopic edge to the skylight connective plate using four M6 bolts.
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
10 Installing the Aisle Containment
(2) Skylight connective plate
(4) Cabinet