FusionModule2000 Smart Modular Data Center
Installation Guide
17.6 Cable Routes for the Single-Row Aisle Containment
Scenario (Smart Busway)
Figure 17-12 Routing power cables and signal cables
(1) General input unit
(4) Signal cable
Issue 02 (2018-03-31)
Ensure that strong-current cables and weak-current cables are at least 100 mm away from
each other.
Connect the power cables from the general input unit side to the smart module.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(2) Power distribution unit
(5) Network cabinet
17 Connecting Cables
(3) Conversion unit
(6) Power cable