Procedure
Step 1 Connect one end of the base ground cable to any of the base ground points, and connect the
other end to the general ground bar of the equipment room.
Figure 4-18 Base grounding diagram
(1) Base ground point
Figure 4-19 Connecting the ground cable between the base and cabinet
----End
Issue 02 (2018-03-31)
Alternatively, connect one end of the base ground cable to any of the base ground points, and connect
the other end to the ground bar at the rear door bottom inside the cabinet.