FusionModule2000 Smart Modular Data Center
Installation Guide
(A) Mounting holes for securing a door
frame to a 2000 mm high cabinet
3.
Step 3 Secure the door panels.
Before securing door panels, measure the door panel size. The door panels should be 2045 mm (± 2 mm)
long and 600.5 mm (± 2 mm) wide.
1.
Issue 02 (2018-03-31)
Figure 10-54 Installing a door frame
Tighten all screws on the door frame.
Stand the door panels and remove the four rubber strips from the two door panels.