FusionModule2000 Smart Modular Data Center
Installation Guide
Table 10-6 Sliding door components
No.
1
2
3
4
5
6
7
8
9
Preparations
Tools: adjustable wrench, torque wrench, Phillips screwdriver, flat-head screwdriver, socket
wrench, step ladder, level
Materials: sliding doors and accessories
Procedure
Step 1 Install the door frame.
1.
2.
Issue 02 (2018-03-31)
Pull the post side panel upwards off the clips, as shown by (1) and (2) in
Secure the left and right posts to the upper frame mounting kit using eight M6x16 screws,
as shown by (3) in
Figure
To facilitate assembly, lay the posts and upper frame installation kit on the floor.
After the assembly is complete, verify that the posts are flush with the upper frame mounting kit.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Name
Aisle door fittings
Posts
Upper frame mounting kit
Guide rail
Glass doors
Stop blocks at the end of the
guide rail
Dampers
Hanging kits
Door boxes
10-32.
10 Installing the Aisle Containment
Remarks
Seal the bottom of a 2000
mm high end cabinet.
The door frame consists of
an upper frame mounting kit
and the left and right posts.
Hangs a sliding door.
Slide rightward and
leftward.
Limit the position of the
door at both ends of the
guide rail.
The dampers are left and
right sensitive.
The dampers are left and
right sensitive.
The door boxes are left,
middle, and right sensitive.
Figure
10-32.
122