Troubleshooting Procedure - ABB ACS5000 User Manual

Medium voltage ac drive air-cooled, 2 - 7 mva
Hide thumbs Also See for ACS5000:
Table of Contents

Advertisement

Chapter 10 - Preventive and corrective maintenance
10.3.4

Troubleshooting procedure

10-6 (36)
2. +Fault PPCS Communication occurred 2 min 22 sec later than
the first fault due to another fault in the drive.
1. +Fault AMC: Fault Class 2 informs about the pending fault class.
For further information on alarms and faults, see
parameter
table.
If a fault shuts down the drive, proceed as follows:
1
Do not switch off the auxiliary power supply or try to reset a fault
message before all information at the time of the occurrence of the
fault condition has been saved.
2
Call up the Fault History Display on the CDP control panel.
For further information, see
Do not clear the fault buffer of the drive now!
3
Identify the fault and make a logbook entry.
Note the fault message displayed on the CDP control panel and look
up the fault message in the Alarms and Faults Troubleshooting Guide
for further information.
4
Save the content of the data logger when a PC is available that has
the DriveWindow or DriveDebug installed.
The data logger provides information (eg, waveforms of voltage,
current, torque) for efficient troubleshooting.
5
If a fault cannot be rectified, contact ABB service.
When calling ABB service, it is recommended to have the following
data available at the time when the fault occurred:
Operating, ambient and load conditions
Unusual events
After the fault has been rectified, start the drive as described in
-
Operation.
3BHS221906 ZAB E01 Rev. D
Appendix G – Signal and
Chapter 9 - CDP control
ABB
panel.
Chapter 8
5k A UM

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents