ABB
Insulation tests
1
All power cables to input transformer, between input transformer and drive, and from
drive to motor measured, measured values within the required limits.
2
Test report of the megger test available
If the test is carried out by the commissioning personnel of the drive, an additional day
per drive-motor combination needs to be reserved. After the test, the feeder cables can
be connected, except at the drive end. The test must comply with the specification.
Power supply
1
Medium voltage available for start-up of drive
2
Low voltage auxiliary power available for start-up of drive
Miscellaneous
1
Sufficient number and correct type of spare parts available
2
Air conditioning of drive room ready for load run of drive
3
Optional equipment ready
5k A UM
3BHS221906 ZAB E01 Rev. D
Commissioning check list
3 (4)