8.11 Rules for Deploying T/H Sensors

Context
Issue 01 (2017-07-30)
When installing temperature sensors on the front door, route the sensors through the
sponge strips between the rack rail and side plate, and then secure the sensors.
When installing temperature sensors, bind the cables behind the sensors to the cabinet. The
binding position should be 20 mm away from the sensor probes.
The temperature sensor must not be in touch with metal parts or the cabinet.
Ensure that the temperature sensors installed on the cabinet rear door are on the side
without a PDU2000.
Keep the temperature sensors facing the inside of the cabinets to ensure accurate
measurement of cabinet interior temperatures.
Determine the number of T/H sensors to be deployed based on the number of air
conditioners.
Each air conditioner can be configured with three more external T/H sensors.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.