Huawei FusionModule2000 Installation Manual page 104

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
1. Slightly loosen the M4x12 screws securing the hanging kits to the conversion brackets (do
2. Adjust the gaps between adjacent door boxes, as shown by (2) in
3. Tighten the screws to secure the hanging kits to the conversion brackets, as shown by (3)
----End
Follow-up Procedure
Issue 01 (2017-07-30)
not remove the screws), as shown by (1) in
If the gap is larger at the top and smaller at the bottom, adjust the outer M6 screws
downwards to ensure that the door boxes are in close contact, as shown by A in
5-22.
If the gap is smaller at the top and larger at the bottom, adjust the inner M6 screws
downwards to ensure that the door boxes are in close contact, as shown by B in
5-22.
in
Figure
5-22.
Figure 5-22 Adjusting the gaps between door boxes
Adjust the inner rubber strip to ensure that the two glass doors are in close contact.
If the two glass doors do not align well because the end cabinets are not properly placed,
insert a spacer between the post and fixing position of the backward cabinet, as shown in
Figure
5-23.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installing the Contained Aisles
Figure
5-22.
Figure
5-22.
Figure
Figure
95