FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 4-8 Leveling a cabinet
(1) Level
Step 3 Interconnect adjacent cabinets, as shown in
1.
2.
3.
Issue 01 (2017-07-30)
Remove the M5x10 tapping screws that secure the connecting kits and then remove the
connecting kits.
Remove M4x10 screw assemblies from the position for combining cabinets.
Secure the connecting kit using the M4x10 screw assemblies.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
4-9.
4 Installing Cabinets
63