Huawei FusionModule2000 Installation Manual page 35

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 3-12 300 mm wide fixed base
Procedure
Step 1 Adjust the adjustable feet for the base.
1.
2.
Issue 01 (2017-07-30)
When deploying the base, place the side marked FRONT facing the aisle containment.
After deploying the base, check that the adjustable feet for the base should be installed at
the front door of the air conditioner.
Remove the four M6 screws from the support to split the adjustable feet from the base,
as shown in
Figure 3-13
Figure 3-13 Removing adjustable feet
Move the adjustable feet to the mounting holes on the base according to the depth of the
air conditioner.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
and set aside the screws.
3 Hardware Installation Preparations
26