Huawei FusionModule2000 Installation Manual page 232

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Sealing Plate
600 mm wide, 2000 mm high sealing plate
800 mm wide, 2000 mm high sealing plate
300 mm wide, 2200 mm high sealing plate
600 mm wide, 2200 mm high sealing plate
800 mm wide, 2200 mm high sealing plate
Procedure
Step 1 Determine the positions of sealing plates, directions of the concave sides of sealing plates, and
the area covered by the adjustable skylight based on the actual installation environment and
the description in
Step 2 Install the sealing plates near the aisle.
1.
2.
3.
Issue 01 (2017-07-30)
A.4.1 Scenario
Install the sealing plates near the aisle containment first, and then the sealing plates near the smart
module exterior.
Secure the two sealing plates using three M6 screws and nuts.
Place the connected sealing plates at the specified installation position, facing the correct
direction.
Drill four holes in the floor through the four holes at the bottom of the sealing plate using
a hammer drill with a 15 mm drill bit. Secure the sealing plate to the floor using four
plastic expansion bolts labeled DKBA44091028 and four washers.
If drilling holes in the ESD floor is not supported onsite, use four ST4.8x25 self-drilling tapping screws
and washers for securing.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
BOM Number
21500718
21500720
21500939
21500940
21500941
Description.
A Appendix
223

Advertisement

Table of Contents
loading

Table of Contents