Positioning Bases - Huawei FusionModule2000 Installation Manual

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 3-4 Assembling a base
1.
2.
3.
4.
----End

3.1.1.2.2 Positioning Bases

Procedure
Step 1 Determine the correct installation position for the smart module based on the onsite
engineering layout diagram.
Step 2 Use a laser locator to mark two lines that are perpendicular to each other in a corner of the
planned installation position.
Step 3 Use a marker to mark the outline of the cabinet on the floor and place one corner of the
outline at the crossing point of the perpendicular lines.
Issue 01 (2017-07-30)
Adjust the base depth based on the cabinet depth.
Tighten the six M8x20 bolt assemblies on the telescopic rod using a Phillips screwdriver,
as shown by (1) in
Figure
Assemble the telescopic rod and base using eight M8x20 bolt assemblies, and then
tighten all bolt assemblies using a Phillips screwdriver, as shown by (2) in
Tighten all height locking bolts using a torque wrench, as shown by (3) in
If no laser locator is available, use a right angle and thin rope for marking the two perpendicular lines.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3-4.
3 Hardware Installation Preparations
Figure
Figure
3-4.
3-4.
21

Advertisement

Table of Contents
loading

Table of Contents