FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 4-16 Taking out PDU2000 industrial connectors
Step 2 Lay out the PDU2000 industrial connectors and cables on the cabinet top, and reinstall the
rodent-proof mesh.
Cut the rodent-proof mesh based on the cable thickness using a tool such as diagonal pliers. If
the opening is too large, unwanted things may fall into the cabinet through the opening.
Figure 4-17 Laying out PDU2000 industrial connectors and cables
Repeat the preceding steps to take out and preinstall PDU2000 industrial connectors for all cabinets.
----End
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Installing Cabinets