Context
When the air conditioner pipes are routed from the bottom, the water detector is installed in
the network cabinet, and bound to the rack rail at the rear door using cable ties. The binding
position is 5 U away from the cabinet bottom.
Figure 8-77
Figure 8-77 Laying out a water detection cable (bottom pipe routing)
(1) ECC800
Do not contact the water detection cable to metal, for this action will cause a false alarm. Take
protective measures when routing a water detection cable.
Issue 01 (2017-07-30)
shows how the water detection cable is laid out.
(2) Network cable
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Installing Monitoring Devices
(3) Water detector
(4) Water detection cable