FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Step 2 Tear off the protection paper from the rear of the fastener, and then securely attach the
fastener to the floor.
Figure 8-74 Installing a fastener
When securing the water detection cable to the concrete floor, use the cable nail clips delivered with the
cable to secure the cable.
Figure 8-75 Installing a cable nail clip
Step 3 Place the water detection cable onto the fastener, secure the fastener, and keep the water
detection cable in close contact with the floor, as shown in
If multiple water detection cables need to be connected in series, connect the male connector of one
cable to the female connector of another.
Figure 8-76 Securing a water detection cable
----End
Issue 01 (2017-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Installing Monitoring Devices
Figure
8-76.
176

Advertisement

Table of Contents
loading

Table of Contents