Huawei FusionModule2000 Installation Manual page 52

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Procedure
Step 1 Use a pallet truck to transport the UPS to the installation position.
Step 2 Check the UPS packing.
Step 3 Cut off and remove the binding tapes, as shown in
Figure 3-31 Removing binding tapes
Step 4 Remove packing materials, as shown in
Issue 01 (2017-07-30)
Only trained personnel are allowed to move the UPS. Use a pallet truck to transport the
UPS box secured to a wooden support to the installation position.
To prevent the UPS from falling over, secure it to a pallet truck using ropes before moving
it.
To prevent shocks or falls, move the UPS gently. After placing the UPS in the installation
position, unpack it and take care to prevent scratches. Keep the UPS steady during
unpacking.
If the UPS installation environment is in poor condition and the UPS will be stored for a
long time after it is unpacked, wrap the UPS with the original plastic coat to prevent dust.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation Preparations
Figure
3-31.
Figure
3-32.
43

Advertisement

Table of Contents
loading

Table of Contents