Cable Installation For The Power Supply And Distribution System; Connecting Battery Cables - Huawei FusionModule2000 Installation Manual

Smart modular data center 2000 mmhigh cabinets, dual-row aisle containment, 208 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Dual-Row
Aisle Containment, 208 V)
Figure 11-25 Connecting the ground cable between the base and cabinet
11.10 Cable Installation for the Power Supply and
Distribution System

11.10.1 Connecting Battery Cables

Precautions for Connecting Battery Cables
When installing batteries, install battery trays at first, and then place batteries onto the trays
and connect cables. Do not move all the batteries into the cabinet after placing them on the
trays and connecting cables.
Issue 01 (2017-07-30)
Connect one end of the base ground cable to any of the base ground points shown by (1)
in
Figure
11-24, and connect the other end to the general ground copper bar of the
equipment room.
Connect one end of the base ground cable to any of the base ground points shown by (1)
in
Figure
11-24, and connect the other end to the ground copper bar at the rear door
bottom inside the cabinet, as shown in
cables by following instructions in
For details about how to connect battery cables, see the battery cable connection diagram
delivered with the cables.
Battery trays consist of supports and trays, with space reserved between supports and
trays on adjacent layers for operation before battery cabinets are delivered. To remove
the battery trays, perform the following operations:
a.
Remove the battery trays from top to bottom.
b.
Install batteries and connect cables from bottom to top.
When placing batteries, install separators between adjacent batteries, as shown in
11-26. If the battery capacity is 65 Ah or more, there is no need to install a separator in
the depth direction of the battery cabinet. After placing the batteries, attach the battery
labels on the middle position at the battery top from positive terminals in sequence based
on the wiring diagram, as shown in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
11-25. Then connect the module ground
11.9.3 Grounding
Cabinets.
Figure
11-27.
11 Cable Routing
Figure
202