Context
Table 3-6 Hoisting precautions
Stage
Before hoisting
During hoisting
Tools: marker, ink fountain, long leather measuring tape, crane, socket wrench,
torque wrench, Phillips screwdriver, jack, steel hoisting rope, level, level gauge,
hammer drill, angle ruler, claw hammer, vacuum cleaner
Materials: device to be hoisted, expansion bolt, angle steel bracket
Procedure
Step 1 Prepare concrete platforms.
Figure 3-4 Concrete platforms for a single unit (unit: mm)
Issue 02 (2021-04-15)
Precautions
Ensure that the crane and steel ropes provide the required
bearing capacity.
The doors of devices to be hoisted are closed.
Ensure that the steel ropes are securely connected.
Do not allow any unauthorized people to enter the
hazardous areas and never stand under the crane arm
during hoisting.
Ensure that the crane is properly located and avoid long-
distance hoisting.
Ensure that the device is stable and the diagonal gradient
of the device is less than or equal to 5 degrees.
Lift and land a device slowly to prevent shock to equipment
inside it.
Remove the steel ropes after ensuring that the device is
placed evenly on the concrete platforms.
Copyright © Huawei Technologies Co., Ltd.
3 System Installation (Building Scenario)
38

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusioncol8000-e240h4

Table of Contents