Operating Instructions Fire alarm system EBL512 V2.3.x

Commissioning an installation

Before you connect the power supply to a control unit, all other cable
connections shall be made. Check once more that they are correct.

Single Control Unit

1. Take away the rectifier fuse (F1) and a battery fuse (F2 or F3) on
the charger board 1557 / 1657.
2. Connect the batteries to the charger board 1557 / 1657.
3. Connect the rectifier to the mains (230 V AC).
4. Replace the rectifier fuse (F1) and the battery fuse (F2 or F3) on
the charger board 1557 / 1657.
5. LED "Operation" (L6) indicate that the 24 V DC power supply
(rectifier and/or battery) is okay.
6. An automatic restart will now take place (see chapter "Restart",
page 69.
7. The site specific data (SSD) can now be downloaded, see chapter
"Programming (SSD download)", page 63.
See also chapter "Calibration of supervised outputs (H5/A1)", page
105.

Control Units in a TLON network

In a TLON network there are two or more control units connected. A
TLON connection board 1590 is required in each control unit
connected to the network. When the 1590 board is on place and the
56
cables connected
, for each control unit, do as follows:
1. Take away the rectifier fuse (F1) and a battery fuse (F2 or F3) on
the charger board 1557 / 1657.
2. Connect the batteries to the charger board 1557 / 1657.
3. Connect the rectifier to the mains (230 V AC).
4. Replace the rectifier fuse (F1) and the battery fuse (F2 or F3) on
the charger board 1557 / 1657.
5. LED "Operation" (L6) indicate that the 24 V DC power supply
(rectifier and/or battery) is okay.
6. An automatic reset/restart will now take place (see chapter
"Restart", page 69.
56
The TLON connection board is to be mounted on the main board 1556.
Cable connections are to be made on the connection board 1555 (T.B. P1).