17.2.1
Operating Instructions Fire alarm system EBL512 V2.3.x
See also chapter "Calibration of supervised outputs (H5/A1)", page
105.
When all control units are running (power supplied)
network programming (configuration) has to be done before the site
specific data (SSD) can be downloaded, see chapter "Programming
(SSD download)", page 63.

TLON network programming (configuration)

A PC is connected to the modular connector J2 in the control unit
(main board 1556). The PC program TLON Manager is used, see
separate TLON network documentation.
57
If one or more of the control units are to be started-up later, do as follow:
- Do all the programming for the whole project (system) in TLON Manager.
- Do all the Win512 programming of SSD for the whole system (all control
units). Wait to do the download the SSD until the TLON Network
programming is ready for the control unit respectively.
- Start-up the wanted control units according to chapter "Control Units in a
TLON network", page 61 (i.e. power on and TLON Network programming of
the control unit respectively).
- Since not all control units are started-up in the project (system), "FAULT:
CU xx has no contact with CU xx" will be shown for the "missing" control
units.
- Later, when one or more control units are stated-up, do also "Update all"
and "Save all" in TLON Manager.