6.8.2 Configuring PUE User-defined Mode

Context
This section describes how to configure PUE for the integrated PDC connected.
The functions of configuration buttons for the PUE user-defined mode are described as
follows.
Table 6-37 PUE configuration buttons
No.
1
2
Procedure
Step 1 Log in to the ECC800-Pro WebUI as an administrator.
Step 2 Choose System Settings > PUE Configuration.
Step 3 Set PUE function to Enable.
Step 4 Set PUE configuration mode to User-defined, and click Submit.
1.
Issue 06 (2020-04-22)
Figure 6-41 Querying the total electrical energy of system IT load output
Calculate the PUE of the smart module. PUE = Increment in total system input electrical
energy/Increment in total electrical energy of system IT load output = 10.0 kWh/6.0
kWh = 1.67.
Button
Description
Adds new total power consumption or IT power consumption
Add
parameters.
Delete
Deletes a parameter setting for the total power consumption or IT
power consumption.
On the Total Power Consumption Configuration tab page, click Add to enter the
Total Power Consumption Configuration page. On the Select Device tab page, select
Integrated PDU 1. On the Select Indicators tab page, select Total active electricity
energy of PDU input, and click Confirm.
Copyright © Huawei Technologies Co., Ltd.
6 Feature Description
175

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ecc800-pro

Table of Contents