5.3.13.1 NetEco6000 Management

5.3.13.1.1 Connecting a Communications Cable

Procedure
Step 1 Connect the communications cable to the WAN1 port on the ECC800-Pro.
Figure 5-50 Connecting the communications cable
----End

5.3.13.1.2 Setting NetEco Parameters

When the smart module can be connected to the NetEco, perform the following
steps to configure parameters.
Procedure
Step 1 Apply for a fixed IP address to the equipment room network administrator.
Step 2 Set the IP address, subnet mask, and default gateway on the ECC800-Pro WebUI.
Table 5-23 IP parameters
Path
System
Settings >
System
Parameter
s >
Monitor IP
> WAN_1
Step 3 Click Submit.
Step 4 Set the NetEco communication parameters and authentication password on the
ECC800-Pro WebUI.
Issue 02 (2020-12-25)
Parameter
Default
Value
IP address
192.168.8.1
0
Subnet
255.255.25
mask
5.0
Default
192.168.8.1
gateway
Copyright © Huawei Technologies Co., Ltd.
5 Power-On Commissioning
Setting
Set this parameter based on the IP
address assigned by the network
administrator.
Set this parameter based on the
subnet mask assigned by the network
administrator.
Set this parameter based on the
default gateway address assigned by
the network administrator.