Cable Binding Requirements
Bind cables reliably along the route and ensure that the binding interval meets the
requirements in
Table 4-14 Cable binding interval
Cable Diameter (mm)
< 10
10–30
> 30
1.
Issue 02 (2020-12-25)
Figure 4-97 Cable connection positions
Before installing a semi-flexible cable, use a dedicated tool to curve the cable.
Do not curve the cable while holding the cable connector by hand.
If a number of wire terminals are connected to a multi-point connector,
provide slack and arrange them neatly to prevent stress on certain wires, as
shown in
Figure
4-98.
Figure 4-98 Cable connections
Protect cable holes in a metal kit with grommet strips. Alternatively, ensure
that the holes are rounded, free from burrs or sharp edges.
Keep cables far away from heat sources such as radiators and heat vents. If
unavoidable, take heat resistant measures.
Keep cables far away from operating components such as fan blades and do
not bind cables to an airflow path of fans.
Prevent rotating components such as doors from squeezing or pulling cables.
Table
4-14.
Bind cables with a moderate force and ensure that cables are not misshapen
to prevent compromising the signal quality.
Copyright © Huawei Technologies Co., Ltd.
Binding Interval (mm)
150
200
300
4 Installation Guide