FusionModule500 Smart Mini Data Center
User Manual
Procedure
Step 1 Install busbars.
1.
2.
3.
----End

4.2.5.3 Installing PDU2000s

Context
Two half-height rPDUs for vertical installation are configured.
Procedure
Step 1 Install a half-height PDU2000.
1.
2.
Step 2 Install the other PDU2000 in the same way.
Issue 02 (2020-12-25)
Open the cabinet rear door.
Install floating nuts at the busbar installation position.
Secure the busbar to the installation position using screws.
NO TE
The busbar is installed 2 U above the last lithium battery. Determine the busbar
installation position based on the lithium battery configuration.
Figure 4-42 Installing busbars
Open the cabinet rear door.
Secure the half-height PDU2000 to the installation position using screws.