FusionModule500 Smart Mini Data Center
User Manual
Figure 4-41 Installing a lithium battery
● The lithium battery weighs about 43 kg. Check the load-bearing capability of
● The lithium battery is 396 mm deep. Check the depth of the rack before
● The lithium battery can be installed in a 19-inch rack with guide rails and a
● If multiple lithium batteries are installed, certain clearances should be reserved.
● Install lithium batteries from bottom to top.
Step 2 Install the protective covers for the positive and negative poles of the lithium
batteries.
Step 3 Install other lithium batteries in the same way.
----End

4.2.5.2 (Optional) Installing Busbars

Prerequisites
If there is more than one lithium battery, install busbars.
Install busbars before installing the PDU2000.
Issue 02 (2020-12-25)
NO TICE
the rack tray before installation.
installation.
tray. Check whether the load-bearing capability meets requirements.
The space for each lithium battery should be at least 3 U. The lithium batteries
cannot be directly stacked or vertically placed.
Copyright © Huawei Technologies Co., Ltd.
4 Installation Guide
101