Battery Installation; Figure 3-78 Installing The Chs Large Batt Box Using The Chs2U Joint Bracket Kit; Figure 3-79 Removing Chs Large Batt Box Cover - NEC Univerge SV8100 System Hardware Manual

Hide thumbs Also See for Univerge SV8100:
Table of Contents

Advertisement

UNIVERGE SV8100
System Hardware Manual
2.
Mark and drill the four holes required to install the CHS BASE
UNIT.
3.
Align bolt holes in CHS BASE UNIT (see
Mount Spacing Guide on page
and secure using four anchor bolts.
4.
Align and install the CHS LARGE BATT BOX on top of the CHS
BASE UNIT.
Figure 3-78
Installing the CHS LARGE BATT BOX using the CHS2U JOINT
BRACKET KIT
5.
Secure the CHS LARGE BATT BOX to the CHS BASE UNIT
using the CHS2U JOINT BRACKET KIT. Refer to
Installing the CHS LARGE BATT BOX using the CHS2U JOINT
BRACKET
7.2.2

Battery Installation

1.
Loosen screw on front of CHS LARGE BATT BOX.
KIT.

Figure 3-79 Removing CHS LARGE BATT BOX Cover

Figure 3-77 Floor
3-62) with holes drilled in floor
Figure 3-78
Issue 9.0
3 - 63

Advertisement