logic programmed by the user in place of the logic shown in Figure 4.9-26. The
user-programmed logic is connected internally to the signal "operate completed",
hence this signal is now generated by the user-programmed logic at connection
point#2 "User configurable condition". That is, set the scheme switch [TPOS01-
LGP1EXOT] to PLC and use "TPOS01IN_TMP_38".
Output signal to BO
The TPOS01 function, in Figure 4.9-37, can issue an "Operate" signal at the output point
"TPOS01_P3EX_BO", when the TPOS01 function determines that the "Local-P3-Control"
signal is true.
Receiving "operate command P1-control" using the PLC function
(vii)
Figure 4.9-38 outlines the reception of the operate command 'P1-control' using the PLC
function.
Wait for a command
Select logics
P1 control from the remote-end
P2 control from the remote-end
P3 control from the remote end
P1 control from the local-end
P2 control from the local-end
P3 control from the local-end
P1 control by the PLC function
P2 control by the PLC function
P3 control by the PLC function
Figure 4.9-38 Outline of Operate command 'P1-control'
Input signal from the PLC function
Figure 4.9-39 describes the operate logic when an "Operate command P1 (PLC-P1-Control)"
signal is generated by the PLC function. There are two input points for the reception: the
former connection point (PLC#3) is used for the reception of the operate-command when the
interlock-check is required, the latter connection point (PLC#4) is used for the reception of the
operate-command when the interlock check is not required. That is, for the TPOS01 function
"Operate command P1 (PLC-P1-Control)" signal generated in the user-programmed logic and
when the interlock check is required in the operate logic, apply the signal at connection point
(PLC#3; i.e., DEV01_P1_INTERLOCK).Alternatively, if the interlock check is not required,
Wait for a next command
P1 control from the remote-end
P2 control from the remote-end
P3 control from the remote end
P1 control from the local-end
P2 control from the local-end
P3 control from the local-end
P1 control by the PLC function
Operate logic
Signal generation by the
PLC function
P2 control by the PLC function
P3 control by the PLC function
- 823 -
6F2S1915 (0.46)
Success
Operation
Signal output
decision
Do nothing
Failed