Commissioning
5.3 Creating a project offline
Result
The Control Unit is inserted and can then be configured.
Example: CU310-2 PN inserted
5.3.4.2

Inserting a Control Unit via the portal view

Overview
Alternatively to the recommended main method, you can insert a SINAMICS S120 Control Unit
into a new project via the portal view.
Requirements
• A project has been created (Page 100), or an existing project is open.
• The online connection to the drive is deactivated.
106
Example: CU320-2 PN inserted
Commissioning Manual, 06/2020, 6SL3097-5AA10-0BP2