Huawei ECC800-Pro User Manual page 225

Data center controller
Hide thumbs Also See for ECC800-Pro:
Table of Contents

Advertisement

ECC800 Data Center Controller
User Manual (for ECC800-Pro)
1. It is recommended that you perform a battery shallow discharge test only in a
2. After the UPS is powered off, the battery maintenance period of the UPS will
3. During a battery shallow discharge test, if the mains outage occurs, the backup
Procedure
Step 1 Log in to the ECC800-Pro WebUI as an administrator.
Step 2 Choose System Settings > Linkage Control. Set Enable linkage control function
to Yes and click Submit.
Step 3 Set Battery shallow discharge test to On.
Step 4 On the Linkage Logical List tab page, click Add or the edit icon
Figure 6-69 Setting parameters for Linkage Logic List
----End
Issue 02 (2020-09-07)
NO TICE
class 1 power grid scenario after confirming with the customer. If the power
grid is not stable, do not perform the battery shallow discharge test.
be recalculated.
capacity may be inconsistent with the rated capacity.
Copyright © Huawei Technologies Co., Ltd.
6 Feature Description
.
214