Step 8 Press the CIM networking switch for 2 seconds. When the RF_Z indicator on the CIM turns
from blinking green at super short intervals to blinking green at long intervals, the
replacement is complete. If
in this section.
----End

4.5.3.4 Replacing a Camera

Prerequisites
Procedure
Step 1 Remove the front cover of the camera in the direction shown in
screws on the front cover.
Figure 4-18 Removing the front cover
Step 2 Remove the inner cover, as shown in
Issue 07 (2019-12-20)
By default, the BIM checks the battery internal resistance once every 24 hours. The red indicator is
steady on during the check. You can also choose Monitoring > CIM System > Running Control
on the WebUI and click Internal resistance to manually measure the battery internal resistance.
The battery internal resistance will change to an invalid value after power-off and then power-on
again.
Recommended tools and materials: inner hexagon screwdriver (delivered with the
product package), step ladder (2 m)
A dome camera needs to be replaced.
Spare dome cameras of the same model are available and functional.
Copyright © Huawei Technologies Co., Ltd.
Step 6
fails, replace the BIM again by following the instructions
Figure
4-19.
4 Maintenance
Figure
4-18, and remove