FusionModule500 Smart Mini Data Center
User Manual (ECC800e)
2.2.7.13 (Optional) Installing an Independent Deployment AI/DI Unit
Procedure
Step 1 Determine the mounting holes for the independent deployment AI/DI unit based on the
cabinet layout. Engage floating nuts into appropriate mounting holes in the rack rail of the
cabinet using a floating nut mounting bar. Install two floating nuts on each side. See
2-57.
Figure 2-57 Installing a floating nut
Step 2 Install the independent deployment AI/DI unit in the appropriate position in the cabinet, as
shown in
Figure 2-58 Installing an independent deployment AI/DI unit
Step 3 Set the address for the independent deployment AI/DI unit to 1.
Issue 07 (2019-12-20)
If no floating nut mounting bar is available, using a flat-head screwdriver instead.
Ensure that the floating nuts on both sides are on the same horizontal line.
Figure
2-58.
Copyright © Huawei Technologies Co., Ltd.
2 Installation
Figure
66